France’s plan to build six new nuclear reactors is under threat from low electricity prices, the country’s Court of Auditors has warned. The EDF nuclear reactors France programme, which is central to the government’s energy strategy, could face serious funding difficulties, the state auditor said in a report published on Monday, 16 November 2026, just weeks before EDF is expected to make a final investment decision on the project.
The warning is stark. EDF, the French state-owned utility, could struggle to fund the construction of six new EPR2 reactors, and could require substantial state backing if energy market revenues fail to cover the cost of building, maintaining and operating them. The report also warns that the government may have to forgo about €65 billion in cash profit payouts from EDF between 2026 and 2040, under certain scenarios, to prevent the company from running out of funds during construction.
This post explains what the Court of Auditors said, how much the reactors will cost, why electricity prices matter so much, what the report says about France’s existing reactors, and what the warning means for the final investment decision that EDF is expected to take in the coming weeks.
EDF Nuclear Reactors France: What the Court of Auditors Found
The Court of Auditors, known in French as the Cour des comptes, is France’s public audit body. It examines how public money is spent and whether major public projects are financially sound. Its report on EDF, published on 16 November 2026, looks at the company’s long-term nuclear projects and at the financial exposure it faces across them.
According to Reuters, which reported the findings, the audit body said EDF faces heavy financial exposure across its long-term nuclear projects and could require substantial state backing if energy market revenues fail to cover building, maintenance and operating costs. That is a careful, formal way of saying that the company may not be able to pay for the reactors out of its own earnings, and that the state — which owns EDF — may have to step in.
The timing of the report matters. It comes weeks before EDF is expected to make a final investment decision on the six-reactor programme. A final investment decision is the point at which a company commits to a project in full, after years of planning and preliminary work. The Court of Auditors’ warning is, in effect, a message to the government and to EDF’s board: look at the numbers again before you commit.
How Much the Six New Reactors Will Cost
EDF’s planned construction of six EPR2 reactors is budgeted at €72.8 billion in 2020 values, which the Court of Auditors calculated at €84 billion in 2025 values. The EPR2 is the next generation of the European Pressurised Reactor design, and the six reactors are planned as pairs at three sites. The first commercial operations are scheduled from 2038, according to Reuters.
Those figures are large by any standard, and they are the reason the Court of Auditors is concerned. A project of €84 billion, spread over more than a decade of construction, requires a company that can fund it through years when it is spending heavily and earning nothing from the new reactors. If the company’s other revenues fall short, it can run into trouble long before the first reactor starts generating electricity.
The report also highlights the history of the single Flamanville 3 reactor, which suffered large cost overruns and long delays. Flamanville 3 is the only EPR reactor built in France so far, and its experience is a warning about what can happen when a complex nuclear project goes wrong. The Court of Auditors warned of much larger fiscal exposures across the six planned EPR2 units, implying that the same kind of overrun, repeated across six reactors, would be far more serious than the Flamanville experience alone.
Why Low Electricity Prices Threaten the Programme
The core of the auditor’s warning is about electricity prices. EDF earns its money by selling electricity, and the price it receives depends on the wholesale market. If wholesale prices are high, EDF earns more, and it has more money to invest in new reactors. If prices are low, its earnings fall, and the funding gap for the new reactors grows.
The Court of Auditors said a drop in wholesale electricity prices below €70 per megawatt hour would heavily increase EDF’s financing gap. That threshold is the key number in the report. Below €70 per megawatt hour, the company’s revenues from selling electricity would not be enough to cover the cost of the new reactors alongside its other obligations, and the gap would have to be filled by the state or by other means.
The market data cited by Reuters shows why the warning is not theoretical. While wholesale baseload electricity prices for delivery in 2027 closed on Friday at just under €120 per megawatt hour, the contracts for 2028 and 2029 were at €65.75 and €60.10 per megawatt hour respectively, according to LSEG data. In other words, the market expects prices in 2028 and 2029 to be below the €70 threshold that the Court of Auditors identifies as a danger point.
The Short-Term Price Spike and the Longer-Term Outlook
The contrast between the 2027 price and the 2028 and 2029 prices is telling. The higher 2027 price reflects, in part, short-term disruptions, including the disruption in the Strait of Hormuz and low gas storage levels in Europe, which have pushed up energy costs in the near term. Reuters reports that the lower prices for 2028 and 2029 suggest the market expects that short-term spike to be short-lived.
That creates a difficult position for EDF. The company needs to make a long-term investment decision — whether to commit €84 billion to six reactors that will operate for decades — in a market where prices are volatile and where the longer-term outlook is for lower prices. The Court of Auditors is, in effect, asking whether the company’s business case for the reactors still holds if prices stay low.
One possible answer, suggested by the report, is that the government may have to forgo about €65 billion in cash profit payouts from EDF between 2026 and 2040 under certain scenarios, to prevent the company from running out of funds during construction. That would mean the state, as EDF’s owner, giving up dividends it would otherwise receive, so that the money stays in the company to fund the reactors. It is a large sum, and it shows the scale of the financial support that may be needed.
What the Report Says About France's Existing Reactors
The report is not only about new reactors. It also looks at France’s existing nuclear fleet, which provides the majority of the country’s electricity and is one of the largest in the world. The Court of Auditors said that extending the operational life of EDF’s existing reactors to 60 years remains France’s cheapest low-carbon power option, provided safety approvals are secured and maintenance costs remain strictly controlled.
That finding is important because it offers a cheaper alternative to building new reactors, at least in the short to medium term. Extending the life of existing reactors is less expensive than building new ones, and it uses infrastructure that is already in place. But it is not without risk: the reactors are ageing, they need careful maintenance and safety checks, and the cost of that maintenance has to be kept under control for the extension to remain the cheapest option.
The report therefore presents the government with a choice, or at least a balance to strike: invest heavily in new reactors, with all the financial risk that involves, or make the most of the existing fleet for longer, while deciding how and when to build new capacity. In practice, France is likely to do both, but the Court of Auditors’ warning suggests the balance and the timing need careful thought.
What Happens Next for EDF and the French Government
The immediate next step is EDF’s final investment decision, which is expected in the coming weeks. That decision will be taken by EDF’s board, but it will be closely watched by the government, which owns the company and which has made nuclear power a central part of its energy and climate strategy. The Court of Auditors’ report will be part of the background to that decision, and it may lead to conditions being attached to it, such as a clearer commitment of state support or a revised financing plan.
Longer term, the report raises questions about how France pays for its energy transition. Nuclear power is low-carbon, which makes it attractive for a country trying to cut emissions, but it is also capital-intensive, which makes it vulnerable to changes in electricity prices and to cost overruns. The government will need to decide how much risk the state is willing to take, and how much it is willing to pay, to keep the nuclear programme on track.
For now, the Court of Auditors has done its job: it has warned, in public, that the numbers do not add up as easily as they once did, and that the state may have to pay a large price to keep the programme going. Whether the government and EDF heed that warning, and how they respond, will become clear when the final investment decision is announced.
For more on energy policy, see our report on Trump’s wind turbine import negotiations.
Sources: Reuters – French court of auditors warns low power prices threaten EDF reactor programme, Reuters – Europe hunts for Palantir alternatives, Reuters – French manufacturing back in contraction in October.